Hi DepthAI Fans!
So we ordered the last of everything for our first production run last Friday (December 13th).
Most was actually ordered prior to this date (particularly long-lead parts, like the image sensors, which are 16-week lead),but the last of the shorter-lead parts (power supplies, raspberry pi compute modules, etc.) went out on Friday.
So as of now, we are on-track for shipping February 14th, as planned!
Thanks to everyone who supported the Crowd Supply. We’re excited and looking forward to getting you your units!
Cheers,
Brandon and The Luxonis Team