I have finished building up all 137 units I had left from the last production run and they’re ready to go:
Unfortunately, even though that number covers all orders due to be shipped by 10/26, they aren’t all the right type. I’m 12 units with the regular header short to be able to fill the orders due on 10/26 right now.
I just visited my CM and it seems they are a bit swamped at the moment, but they estimate that they will start assembly of the new 1000-unit run at the end of this week. That will hopefully give me enough time in the next two weeks to finish up the first batch and make my due date!
The good news is that this new batch is more than enough to cover all orders placed up till now, so I should be able to fill most remaining orders hopefully before the end of the year. :)