View Purchasing OptionsProject update 17 of 24
Unfortunately, some of the components used in the LimeRFE design have proven difficult to source reliably, and there is some question about their availability going forward. With that in mind, we took the decision to update our design to accommodate alternative parts. Together with general issues related to component lead times, this delay caused us to miss our August ship date. We now have a revised date and will commence the shipment of backer rewards during the week of 26th October.
I would like to take this opportunity to personally thank backers for their patience and to note, in closing, that we are committed to providing another manufacturing update within the next four weeks.
Ebrahim Bushehri
CEO, Lime Microsystems
LimeRFE is part of Qorvo RF Accelerator