IQ is excited to let you know that we have initiated the manufacturing process for the Fortiq modules! We truly appreciate your patience throughout this process. IQ had several projects in the queue before finalizing Fortiq and due to some unexpected complications, those project timelines got extended much farther than we had expected. Fortunately, IQ recently completed those projects, allowing the team to complete the Fortiq initiative.
IQ expects the timeline to look as such:
Motor & PCB manufacturing lead time: 3 months
Final assembly and calibration: 1 month
Shipping & fulfillment by Crowd Supply: <1 month
With this in mind, we believe these motors will be in your hands in September!