Project update 8 of 9
We have a quick update on the delays we’re experiencing in sourcing and manufacturing the boards. As we mentioned in the last update, sourcing the powerSTEP01 was at the crux of the matter. Well, we now have our hands on whole tray of these bad boys. The supply of this critical component won’t be an issue for a while.
We’ve moved forward and finalized the quote from our CM and have a projected delivery date around the end of May. In total, that equates to a delay of around four to five weeks. We’re disappointed by the reality of this, and we really appreciate the feedback and support of our backers throughout this process.
Thank you.
Wi-Fi Stepper Team